Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • SEARCH
  • Home
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 55911
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 10, 20262026-05-10T17:27:07+00:00 2026-05-10T17:27:07+00:00

Apparently we use the Scrum development methodology. Here’s generally how it goes: Developers thrash

  • 0

Apparently we use the Scrum development methodology. Here’s generally how it goes:

Developers thrash around trying to accomplish their tasks. Generally the tasks take most of the sprint to complete. QA pesters Dev to release something they can test, Dev finally throws some buggy code out to QA a day or two before the sprint ends and spends the rest of the time fixing bugs that QA is finding. QA can never complete the tasks on time, sprints are rarely releasable on time, and Dev and QA have a miserable few days at the end of the sprint.

How is scrum supposed to work when releasable Dev tasks take up most of the sprint?

Thank you everyone for your part in the discussion. As it’s a pretty open-ended question, it doesn’t seem like there is one ‘answer’ – there are many good suggestions below. I’ll attempt to summarize some of my ‘take home’ points and make some clarifications.

(BTW – Is this the best place to put this or should I have put it in an ‘answer’?)

Points to ponder / act on:

  • Need to ensure that developer tasks are as small (granular) as possible.
  • Sprint length should be appropriately based on average task length (e.g. sprint with 1 week tasks should be at least 4 weeks long)
  • Team (including QA) needs to work on becoming more accurate at estimating.
  • Consider doing a separate QA sprint in parallel but off-set if that works best for the team
  • Unit testing!
  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. 2026-05-10T17:27:08+00:00Added an answer on May 10, 2026 at 5:27 pm

    My opinion is that you have an estimation problem. It seems that the time to test each feature is missing, and only the building part is being considered when planning the sprint.

    I’m not saying it is an easy problem to solve, because it is more common than anything. But things that could help are:

    • Consider QA as members of the dev team, and include them in the sprint planning and estimating more closely.

    • ‘Releasable Dev tasks’ should not take up most of the sprint. Complete working features should. Try to gather metrics about dev time vs QA time for each kind of task and use those metrics when estimating future sprints.

    • You might need to review your backlog to see if you have very coarse grained features. Try to divide them in smaller tasks that could be easily estimated and tested.

    In summary, it seems that your team hasn’t found what its real velocity is because there are tasks that are not being considered when doing the estimation and planning for the sprint.

    But in the end, estimation inaccuracy is a tough project management issue that you find in agile-based or waterfall-based projects. Good luck.

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Ask A Question

Stats

  • Questions 64k
  • Answers 64k
  • Best Answers 0
  • User 1
  • Popular
  • Answers
  • Editorial Team

    How to approach applying for a job at a company ...

    • 7 Answers
  • Editorial Team

    How to handle personal stress caused by utterly incompetent and ...

    • 5 Answers
  • Editorial Team

    What is a programmer’s life like?

    • 5 Answers
  • added an answer Joel wrote a nice essay about this very topic: Things… May 11, 2026 at 10:58 am
  • added an answer Your code violates the single responsibility principal in a pretty… May 11, 2026 at 10:58 am
  • added an answer alert('\u20AC'); HTML Entity Character Lookup May 11, 2026 at 10:58 am

Related Questions

Apparently we use the Scrum development methodology. Here's generally how it goes: Developers thrash
We (apparently) had poorly executed of our Solaris MySQL database engine last night. At
We've installed Windows Search Server Express on one of our servers, which apparently runs
Apparently using the URL is no good - why is this the case, and
Apparently xrange is faster but I have no idea why it's faster (and no
Apparently there's a lot of variety in opinions out there, ranging from, " Never!
Apparently you can easily obtain a client IP address in WCF 3.5 but not
Apparently, they're confusing. Is that seriously the reason? Can you think of any others?
Apparently I can't move files on different volumes using Directory.Move. I have read that
apparently it works Can you name reasons beyond good practices not to give these

Trending Tags

analytics british company computer developers django employee employer english facebook french google interview javascript language life php programmer programs salary

Top Members

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.