Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • Home
  • SEARCH
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 283965
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 12, 20262026-05-12T05:25:05+00:00 2026-05-12T05:25:05+00:00

As a developer, I sometimes come across the term ‘Critical Path’ in the context

  • 0

As a developer, I sometimes come across the term ‘Critical Path’ in the context of development execution.
From wikipedia I know it has to do with identifying the necessary tasks that must be completed in a project.

Is my understanding correct?

What is the best definition of Critical Path you have encountered?
How would identify the Critical Path when planning a project?

  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. Editorial Team
    Editorial Team
    2026-05-12T05:25:06+00:00Added an answer on May 12, 2026 at 5:25 am

    I’m not sure if it’s the best definition, but it’s certainly one of the most succinct:

    The sequence of dependent steps that
    determine the minimum time needed to
    carry out an operation

    another, slightly longer one, and in the context of project management (similar to the Wikipedia article that you linked to):

    The path through a series of activities, taking into account
    interdependencies, in which the late
    completion of activities will have an
    impact on the project end date or
    delay a key milestone (there may be
    more than one critical path)

    Your understanding is correct, and the first step to identifying the critical path through a given project, would be to firstly actually define all of the individual steps required to complete the project, then to examine each and every “step” to determine just how dependent/important that step is to both other steps in the project as well as the project overall.

    Let’s say I want to paint a wall. The steps might be (this is an intentionally simplified example):

    • Buy some paint
    • Buy some paint brushes
    • Paint the wall

    Well, given that the end result would be a nice, freshly painted wall, the first step here (Buy some paint) is absolutely critical to the whole thing. If I can’t achieve that, everything else stops. Also, every step after that is entirely dependent upon step 1 having been completed previously. Therefore, in this (admittedly contrived) example, the first step in the critical path is buying some paint.

    Conversely, Step 2 is important for a good paint job but could potentially be omitted if I just throw the paint at the wall!

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Ask A Question

Stats

  • Questions 357k
  • Answers 357k
  • Best Answers 0
  • User 1
  • Popular
  • Answers
  • Editorial Team

    How to approach applying for a job at a company ...

    • 7 Answers
  • Editorial Team

    What is a programmer’s life like?

    • 5 Answers
  • Editorial Team

    How to handle personal stress caused by utterly incompetent and ...

    • 5 Answers
  • Editorial Team
    Editorial Team added an answer The other answers are correct. Here is some code you… May 14, 2026 at 9:40 am
  • Editorial Team
    Editorial Team added an answer you ruin the noConflict concept by reassigning the jquery to… May 14, 2026 at 9:40 am
  • Editorial Team
    Editorial Team added an answer If you get that particular error, you don't actually have… May 14, 2026 at 9:40 am

Related Questions

No related questions found

Trending Tags

analytics british company computer developers django employee employer english facebook french google interview javascript language life php programmer programs salary

Top Members

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.