Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • SEARCH
  • Home
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 73029
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 10, 20262026-05-10T20:08:14+00:00 2026-05-10T20:08:14+00:00

I am about to join a new software team midway through a project. They

  • 0

I am about to join a new software team midway through a project. They are using ExtremePlanner to track their progress.

While they tracking tasks completed, they are not tracking how the estimated size of the project is changing over time. In the short time I have been monitoring the project this estimate has changed faster than the completion rate of the tasks. My gut feeling says that this is not just a blip but a problem that has been consistent throughout the project lifetime.

But how do I prove or disprove this?

I have not found the ExtremePlanner metrics useful for this. I have been exporting the data to MS Excel but the exported task and story info is missing important data like the creation date. Working around this is a bit of work. Is there a better way of doing this?

Alternately am I making too much of this? It has been argued by some of my prospective team mates that since no new features have been added that the scope has not changed and it is not a problem. However I argue that since new work within the features is continually being found the scope is changing and that this needs to be taken in to account when estimating the release date.

  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. 2026-05-10T20:08:15+00:00Added an answer on May 10, 2026 at 8:08 pm

    If this is an Agile project (e.g., using Scrum, XP, etc.), then presumably you are working in iterations (or sprints).

    So my question would be – do things change so frequently within a single iteration that you need to measure those? Typically an agile project steers by freezing functionality within a single iteration. Yes, you may discover new possible implementation details or technical hurdles, but either they are just details within a 2 week iteration.

    If you iterations get too long, I do see your concerns, since you’d be going a bit long to course correct if it takes a month or 6 weeks for each iteration.

    I guess I’d ask – what would you do if you had these reports, and what would be on them?

    A baseline of what the task estimates were originally and what they are now? ExtremePlanner does provide information on Original Estimates for tasks so you can compare those against the current state of the iteration (see the Task view – you may need to click the ‘customize’ link for that view to display the original estimate column).

    If it’s something more, I’d be interested in what you would find useful there (we use ExtremePlanner also and haven’t run into this need, though we use 2 week iterations).

    Hope this helps.

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Related Questions

I'm about to join a new (Java) development team and a thought came to
This question came about because the cells gem specifies template directories using File.join('app','cells'). That
We are about to start a new project. It will be a group of
I'm starting a new project and although I'm used to MySQL, I'm worried about
I'm new to MySQL and am trying to learn more about the JOIN function.
I have a quite complex multi-join TSQL SELECT query that runs for about 8
About project: I'm trying to write CMS-like web-site on Java. Previously I used PHP
About 10 years ago, I was using a computer language called INFO on an
Hello I am new to python and have a question about the best/pythonic way
I am pretty new to image capturing using java. Just started working in java.

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.