I am developing a MSProject add-in with VSTO and I have a question about debugging.
How do I use the Start Option->Command line arguments to load a specific MS Project file?
I have tried using [drive:][path]filename.mpp but the file doesn’t load.
Otherwise everything is fine. I can load a file manually and debug properly.
Thanks for any assistance.
You can use the following command line example to load MS Project with a specific MPP file:
For Visual Studio Project->Debug->Start Options->Command Line arguments – you can use the path enclosed in quotations. The gotcha here is that you must also assign the Start Action->Start External program for this to work – this is a VS bug.
Use ... and set Start External Program (depending on your Office version):
See MS Office for further MS Project command line reference.