I expected that manualy scheduled tasks will not change their dates automatically despite of all other things happened in the project. My Boss says that meeting will be at some fixed date. All previous and later tasks must adjust to that date.
Manipulating the task dates prior to the meeting dates constantly change the fixed dates of the meetings “over and over”. I must still remember that the meeting dates might be changed without notice. And what if I have 5 meetings in my project?
That behaviour makes lots of dalay in my work on my project. It takes me as lot as 1 working day of work to prepare 40 task’s project.
Help me with this, please. It seems my work is not effective. Why is that?
Chris
This depends on the kind of constraint. There are
I’d assume you’re using a semi-flexible constraint while you really want to use an inflexible one. Microsoft’s online help describes constraints in detail – this should solve your problem.