Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • Home
  • SEARCH
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 77187
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 10, 20262026-05-10T20:47:27+00:00 2026-05-10T20:47:27+00:00

I want to implement Scrum, but I can’t decide on a Sprint length. Ken

  • 0

I want to implement Scrum, but I can’t decide on a Sprint length. Ken Schwaber seems to relate that 30 days it the defacto… but I can’t imagine waiting 30 days without the possibility of changing direction or reprioritizing.

Our projects usually only last 1-3 months using the waterfall method and moving to Scrum would probably mean less opportunity to fine tune.

I was thinking about 1 week sprints, but this seems like Scrum Micro Management.

Having 2 week sprints would probably be ideal, but I want to know if others out there were able to implement this successfully. What are the downsides? Is it more work/less work/same about of work to manage a team with shorter sprints?

BTW… 3 week sprints seem odd to me, who does a 3 week sprint? Why not just make it 4 weeks. 😉

  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. 2026-05-10T20:47:28+00:00Added an answer on May 10, 2026 at 8:47 pm

    I’ve worked on teams doing 1, 2 and 4 week sprints. It really is dependent on your organization. I prefer 1 or 2 week sprints. The current team I’m running is at 4 week sprints because we are coordinating efforts of 12 different products. I’m looking to move them to 2 week iterations soon.

    The key thing to defining length is getting to ‘done, done’. For some teams, this means in production. For others, it may mean verified by the business to meet their needs using an internal release. I’d start by defining done, done, then looking at how to structure your sprints around that. Ideally all stories are getting to done at the end of the sprint – and you aren’t just doing Scrummerfall.

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Ask A Question

Stats

  • Questions 72k
  • Answers 72k
  • Best Answers 0
  • User 1
  • Popular
  • Answers
  • Editorial Team

    How to approach applying for a job at a company ...

    • 7 Answers
  • Editorial Team

    How to handle personal stress caused by utterly incompetent and ...

    • 5 Answers
  • Editorial Team

    What is a programmer’s life like?

    • 5 Answers
  • added an answer Sadly, you still have to split it into separate characters,… May 11, 2026 at 1:48 pm
  • added an answer Without specific examples this is hard to decide. While friend… May 11, 2026 at 1:48 pm
  • added an answer <ListBox> <ListBox.ItemContainerStyle> <Style TargetType='ListBoxItem'> <EventSetter Event='MouseEnter' Handler='_listBoxItem_MouseEnter'/> </Style> </ListBox.ItemContainerStyle> </ListBox> May 11, 2026 at 1:48 pm

Related Questions

No related questions found

Trending Tags

analytics british company computer developers django employee employer english facebook french google interview javascript language life php programmer programs salary

Top Members

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.