Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • SEARCH
  • Home
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 172035
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 11, 20262026-05-11T13:05:39+00:00 2026-05-11T13:05:39+00:00

I’m starting to learn about Scrum, and I’m interested in trying it out with

  • 0

I’m starting to learn about Scrum, and I’m interested in trying it out with our development team. I have a lot of questions about it…but my biggest mental roadblock is in the actual graphical design.

With our current development cycle [waterfall-esque], our graphical designer lays out the page with all the imagery and such based on a loose PRD. If we were to utilize the methods of Scrum, how would this development take place? I think we’re used to seeing the big picture and driving towards it…as opposed to fitting the visual pieces together as we go, which is what I’d expect the Scrum policy for graphical design to be.

Would it be unheard of to at least wireframe all the functionality in the backlog? Or would it be wiser to–for the first sprint–design its functionality in such a way that we can add the new features of other sprints as we go? (i.e. When it’s time for a new feature, discuss ‘Where would this fit into the current design?’)

  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. 2026-05-11T13:05:39+00:00Added an answer on May 11, 2026 at 1:05 pm

    here’s how I’d suggest you do it (ie, how we have tried to do it)

    Pre-sprint 0: make sure you have a good vision of what you want to do. Doesn’t have to be super detailed, but should not be ‘we want to build a website which is social’

    Sprint 0: Developers tool up – setup the CI servers, work on the deployment scripts etc, so all the basic framework is done. At the end of this, you should be able to push a button (worst case: run a single command on a REMOTE server) which takes the code in your source control system, builds it, packages it, runs all the tests you want on it, reports that back, and if possible, installs it on a test server (or atleast results in a package you can install on the test server).

    At this time, the designer is doing the wireframes. Their aim is to do basic wireframes for as much of the site as you think you need (think sitemap and flow not fields and pixels). Then, when thats done, work out with the PM’s whats most important, and go into detail on that – wireframe. Not pixels YET.

    Project managers and the like are working with the designer and the business/stakeholder, writing up stories and tasks for you lot to do and track. Obviously, they need to have an idea of the sitemap etc to do this.

    This may take more than one sprint. start with one (I recommend 2-3 week sprints – 1 is too short, 4 is too long), see how much you still need to do etc.

    So at the end of sprint 0, you have:

    • Lots of stories, in priority order (you CAN add more later, infact you will always as requirements change)
    • A sitemap (ie, a general idea of what the whole thing is going to contain)
    • Wireframes for the first block of work
    • All your tools are working and setup
    • You CI, bug tracking, source control and deployment systems are in place

    So then you begin sprint 1

    Keep in mind that for the first 3-4 sprints, you will not know how much work you can do in the sprint, so EXPECT to get it wrong! Take off as much work (in the priority order the business/PM has put them in) as you think you can FOR SURE get done. you can always take more later!

    You lot develop those pages, and the designer(s) wireframe up the next block of pages (as determined by the PM’s). Maybe the designer does the art for those pages, so you can do it in the next sprint

    So, you are developing what you have, and the designers are working on stuff for your next sprint.

    Of course, they could have a scrum process going too, just they started a sprint earlier!

    now repeat until you run out of work

    during a sprint, if (say) a requirement changes or something new is added, then a new story is written for that, and it’s scheduled into the work. If it’s super high priority, it may go at the top and be the top item for the next sprint (which will be 1-2 weeks away, usually). Or it may be a nice to have, so it goes at the bottom – the business decides.

    PM’s/designers need to know they can change things, but changes DO have consequences, so it’s not in their (financial) interest to chop and change back and forward. but requirements DO change, and XP and Scrum deal with this better than waterfall.

    Dont forget:

    • you can stop a sprint at any time and go back to planning, eg if the requirements change too much, or you run out of work
    • you can schedule more work than you have time to do, as long as that work hasn’t been committed to (ie, it’s ‘extra’ or ‘stretch’ work)

    Your PM should be able to predict when the project will end – look at how much work you did in the last sprint (your velocity), and divide the amount of work left by that number, and you get the number of sprints to go. Easy.

    Oh, and read up on story points – dont estimate stories in hours or days. Use points. To bootstrap that, just make the first story you estimate (say) an 8 (the sequence is 1,2,3,5,8,13,21,40,60,100,infinite). Then take the second story, and estimate it relative to the first – is it double the work (13)? half the work (5)? about the same (8)?

    At the end of the sprint, add up how many points you did, and that’s your velocity. The max amount of work you can COMMIT to do doing in the next sprint is that amount. You CAN always stop the sprint early, or just pull more work off the backlog etc if you run out early. As you go along, your velocity will stabalize.

    Damn, I’m sure there are books etc on how to run it, so I’ll stop 🙂

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Related Questions

I know there's a lot of other questions out there that deal with this
I have a string like this: La Torre Eiffel paragonata all’Everest What PHP function
I have a French site that I want to parse, but am running into
This could be a duplicate question, but I have no idea what search terms
I don't have much knowledge about the IPv6 protocol, so sorry if the question
I'm trying to decode HTML entries from here NYTimes.com and I cannot figure out
I am trying to loop through a bunch of documents I have to put
I have a .ini file as follows: [playlist] numberofentries=2 File1=http://87.230.82.17:80 Title1=(#1 - 365/1400) Example
link Im having trouble converting the html entites into html characters, (&# 8217;) i
I have just tried to save a simple *.rtf file with some websites and

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.