I’m trying to use SQL, REST or the Jira Api to find out what the velocity of a project is at any current moment in time. Right now I am trying to find the total number of story points assigned/completed for each sprint and version and from this calculate the velocity of the overall project.
The problem is that Greenhopper is an addon to Jira and does not change the Jira database in anyway, so it must store this information about scrum/agile projects elsewhere. Any ideas where this information might be located?
Thank you!
I finally worked it out!
So here is some of the techniques that we use to access data from Jira.
SQL
This SQL statement for example counts all the issues from every point in Jira for each priority.
Also check out… http://confluence.atlassian.com/display/JIRA041/Example+SQL+queries+for+JIRA
REST Api
I have not tried this properly but there is also a set of REST api that you can use to access some of the data from Jira. This documentation is available here: http://docs.atlassian.com/jira/REST/latest/
An example link: https://JIRA_LINK/rest/auth/1/session
Java
Also another useful link for JIRA Java api: http://docs.atlassian.com/software/jira/docs/api/latest/