When estimating tasks, how does one break from the grip of Hofstadter’s law?
Share
Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.
Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
If you can politically: Estimate in small chunks, work in small iterations, and focus attention on what caused the deviation from the estimate to make the next estimate better.
One of the major causes of bad estimates in my experience is the lack of experience actually using the architecture planned for the project. By adjusting the estimates as things become more concrete and clear the estimates get better over time.
The other major cause of bad estimates is bogus estimates. Estimates kept artificially low to win a bid. The only way a consulting firm can break that cycle is give good estimates and win enough projects and deliver on the estimates to earn a reputation that they hit their estimates. Enough clients will respect that to make a reasonable business out of it, but building that up will be hard.