Sign Up

Sign Up to our social questions and Answers Engine to ask questions, answer people’s questions, and connect with other people.

Have an account? Sign In

Have an account? Sign In Now

Sign In

Login to our social questions & Answers Engine to ask questions answer people’s questions & connect with other people.

Sign Up Here

Forgot Password?

Don't have account, Sign Up Here

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Have an account? Sign In Now

You must login to ask a question.

Forgot Password?

Need An Account, Sign Up Here

Please briefly explain why you feel this question should be reported.

Please briefly explain why you feel this answer should be reported.

Please briefly explain why you feel this user should be reported.

Sign InSign Up

The Archive Base

The Archive Base Logo The Archive Base Logo

The Archive Base Navigation

  • SEARCH
  • Home
  • About Us
  • Blog
  • Contact Us
Search
Ask A Question

Mobile menu

Close
Ask a Question
  • Home
  • Add group
  • Groups page
  • Feed
  • User Profile
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Buy Points
  • Users
  • Help
  • Buy Theme
  • SEARCH
Home/ Questions/Q 450089
In Process

The Archive Base Latest Questions

Editorial Team
  • 0
Editorial Team
Asked: May 12, 20262026-05-12T21:50:03+00:00 2026-05-12T21:50:03+00:00

When planning a software project, I wish to force Microsoft Project to keep several

  • 0

When planning a software project, I wish to force Microsoft Project to keep several tasks that are dependent on each other and assigned to the same resource together, without other tasks interleaved by resource leveling.

For example, I have the tasks –

  • Design CDataAccess
  • Implement CDataAccess
  • Optimize CDataAccess

I want them to follow one another in the GANTT without any other task (such as “Design CDBController”) appearing somewhere in between.

This is fairly unique to software development because “context switching” between tasks is a really bad idea.

Here is an example of the problem (which is a cut down version of the real GANTT) –

GANTT Example http://img36.imageshack.us/img36/5483/gantt.png

(As you can see – task 5 jumps in between tasks 2 and 3 because task 7 depends on it. In this particular example I would have wanted task 5 to either be before task 1 or after task 3).

I have a predecessor dependency set, such that optimization must happen after implementation, and implementation must happen after design, but this isn’t sufficient because it means that the tasks follow each other, but not necessarily IMMEDIATELY follow each other.

Playing with priorities can sometimes help, but things soon get too confusing to manage (a random change in priority in one place causes unintended changes elsewhere).

Is there a way to force such a requirement in Microsoft Project? I would have expected the ability to add a predecessor of type “Finish-to-Immediate-Start”…

Things that are possible but have drawbacks –

  • Consolidating the three tasks into one (summing their durations). This is something I wish to avoid because I like smaller tasks in the GANTT. Making time estimates on large tasks is a lost cause – tasks must be small, or time estimates mean nothing.
  • Adding explicit start dates. This doesn’t really solve the problem because it prohibits resource leveling from actually doing anything.
  • 1 1 Answer
  • 0 Views
  • 0 Followers
  • 0
Share
  • Facebook
  • Report

Leave an answer
Cancel reply

You must login to add an answer.

Forgot Password?

Need An Account, Sign Up Here

1 Answer

  • Voted
  • Oldest
  • Recent
  • Random
  1. Editorial Team
    Editorial Team
    2026-05-12T21:50:04+00:00Added an answer on May 12, 2026 at 9:50 pm

    What you’re asking for isn’t directly possible in Project. The best suggestion I have for you is to create a summary task around tasks 1-3, assign the resource to that and remove the assignment from tasks 1-3. This will force the first three tasks to be leveled as a group.

    You lose some power of Project when doing this however: reporting actuals and so forth on individual tasks will be made harder to do.

    • 0
    • Reply
    • Share
      Share
      • Share on Facebook
      • Share on Twitter
      • Share on LinkedIn
      • Share on WhatsApp
      • Report

Sidebar

Related Questions

I'm planning software that's an OLAP application at its heart (it helps analyse metering
I'm planning to build a USB device that has buttons that some software needs
How much and what planning is used for the software projects that you or
I'm planning on creating a game that contains a landscape with objects on it.
I'm planning to propose to my (very small) company that we buy a computer
I'm planning to do a little project to expand my knowledge in programming. The
I'm currently planning a piece of software for dogbreeders and I'm in doubt about
I'm planning on doing more coding from home but in order to do so,
We are planning on moving for MS Source Safe (ouch) to SVN. We are
I was planning to use url routing for a Web Forms application. But, after

Explore

  • Home
  • Add group
  • Groups page
  • Communities
  • Questions
    • New Questions
    • Trending Questions
    • Must read Questions
    • Hot Questions
  • Polls
  • Tags
  • Badges
  • Users
  • Help
  • SEARCH

Footer

© 2021 The Archive Base. All Rights Reserved
With Love by The Archive Base

Insert/edit link

Enter the destination URL

Or link to existing content

    No search term specified. Showing recent items. Search or use up and down arrow keys to select an item.