We set policy to force rebase before delivery if any baseline is recommended.
But we would not recommend baseline everyday. We will do it once in 2 weeks like that.
In between recommend baseline duration, people are often facing issues in functionality as they have not taken latest code base.
Is there any way to force to rebase before each delivery? [irrespective of baseline is recommended or not].
Is it recommended practice to rebase before each delivery?
It is recommended to rebase before delivering, and it usually is based on the “recommended baseline” mechanism.
So even if you said “irrespective of baseline is recommended or not”, I would still suggest you look at “this deliver policy: ‘Rebase before delivery’“.
From UCM policies:
If you don’t recommend baselines on the parent stream, then you need to define a preop deliver trigger (as in this thread):
With
script.pla script which would list all activities of the current stream, checking if the latest activity is arebase.xxxone.